Aug 15, 2014

Work continued this week on the one million gallon ground storage reservoir being constructed to the east of the existing reservoir is moving along. The roof of the structure is connecting the two tanks that are part of the construction. According to the design, the reservoir is divided into two parts that will each hold 500,000 gallons. The design of the reservoir is circular to maximize water flow, and the second chamber would also be a circular chamber located inside the main chamber. The benefit would be that one chamber could be taken out of service for cleaning or maintenance without disrupting the system. Work on the reservoir is expected to be done next month.