Water for Washington

May 29, 2014

Work has begun on the new one million gallon reservoir for Washington. City administrator Brent Hinson said that the initial excavation for the project has begun and the base for the new tank is being poured. Next week, the main contractor will begin casting the panels for the tank. The city is replacing the former tank, to the left of the tower, due to structural problems. The new tank is expected to be complete in November.